This page provides full details of the proposed change, relevant dates and decisions.
What is the issue?
The CM Rules prohibit a change in Capacity Market Unit (CMU) configuration after Prequalification. This prevents Agreement holders from changing CMUs to reflect changes in project development and/or commercial structures. This can limit the commercial flexibility of Agreement holders, increasing the risk of project non-delivery, preventing more efficient commercial structures, and ultimately increasing Capacity Market costs.
What is the proposed solution?
Amend the CM Rules to allow CMUs to be split after Prequalification subject to the total Connection Capacity and Generating Technology Class (and therefore De-rated Capacity) being unchanged. Any Agreements awarded to the CMU would also be split pro-rata to the split of total Connection Capacity between the new CMUs.
StatusTitle Decoration
With Ofgem phase
This is the stage after consultation and after the CMAG has sent a recommendation to Ofgem but before Ofgem has determined whether to approve/reject/send back a CM Rules change.
Next StepsTitle Decoration
Milestone | Date |
Proposal Form Submission | 8 November 2023 |
CMAG Initial Consideration | Meeting 14 (23 November 2023) |
CMAG Development | Meeting 15 (13 December 2023) |
CMAG Recommendation to Ofgem | Meeting 15 (13 December 2023) |
Ofgem Statutory Consultation | TBC |
Implementation | TBC |
Impacts and Related ChangesTitle Decoration
Impacts
Capacity Market Rules Sections
- Rule 4.4.4 – Configuration of Generating Units
Impacted Parties
- Capacity Providers
- EMR Delivery Body
- CM Settlement Body
Related Changes